SPARCRequest Wiki
20250813-Technical Committee Meeting Minutes
Meeting: | SPARC OS Technical Committee |
|---|---|
Date: | Aug 13, 2025 |
Time: | 2:00 pm - 2:28 pm |
MUSC | Greg, Brigette |
Iowa |
|
LaCATS |
|
Children’s National |
|
Case Western |
|
OHSU | Imogen |
Stony Brook Medicine |
|
Morehouse | Helen, Ruvina |
Agenda
Last Meeting’s Minutes
Institutional Updates:
Louisiana Clinical & Translational Science Center:
7/16/2025
Was able to resolve exception error after merging v3.13.0 - overlooked a file that fixed a Ruby 3 bug where, when document uploads aren’t supported, the error message doesn’t display
8/13/2025
Not in attendance
MUSC:
Links are accessible by Open-Source Members
8/13/2025
Update
Working with potential open-source sites. USC would like to onboard by the end of the year, with MUSC providing programming support.
Discussion
Meeting time will be changed from 2 pm due to schedule. Proposed times are 11 am, 1 pm or 4 pm. Imogen shared a conflict if changed to 1 pm - will work only that time if the meeting week changed. All other members have no conflict with proposed times. Brigette will send out a notice when the new time is determined - may be effective with Sept meetings.
Upcoming Releases
SPARC v3.14.0 Release - tentative Sept 2025, may need to be adjusted in line with the Fulfillment release
SPARCFulfillment v.3.7.0 Release - Server & Ruby/Rails upgrade - Fall 2025
SPARCFulfillment v.3.8.0 Release - Late Winter 2026
Oregon Health & Science University:
7/16/2025
SPARC upgrade is still planned but not yet underway. Reviewed at RMID v1.8.0 release for any effects to their application use of the RMID field setting.
8/13/2025
Have conducted an initial review of the upgrade to Spark 3.13.0, originally planning to implement the upgrade in the next sprint, but it might be delayed until September.
Iowa
7/16/2025
Not in attendance
8/13/2025
Not in attendance
Case Western
7/16/2025
Working on SPARC upgrade - originally planned to go to v3.10 but may install v.3.13.0 since it has the Ruby/Rails upgrade. Depends on the effort & amount of time, with at least 30 files to customize with an installation by Aug 1.
8/13/2025
Not in attendance
Children’s National
7/16/2025
Not in attendance
8/13/2025
Not in attendance
Stony Brook:
7/16/2025
Not in attendance
8/13/2025
Not in attendance
Morehouse:
7/16/2025
Still working through getting the study_type_questions (application Confidentiality section - non Epic questions) displaying. Has disabled the feature pending resolution. Will try running task to add group 3 questions and see if that resolves. Otherwise, may manually add the 2 non-Epic questions.
(Post meeting)
Reviewed Catalog % of Fee options and its relation to service pricing when only Federal and Corporate sources apply. Suggest using override, as % of Fee does not allow percentages less than the set federal % of fee.
Confirmed that new services would have to be added within Catalog to add to requests if they are not in SPARC before a request has been submitted. Adding services is preserved for Catalog Managers. Service provides can perform the action if given that access, if desired.
8/13/2025
Upcoming meeting for SPARC walk through, focused on the service provider actions.
An additional, technical meeting will be scheduled to make sure connections are working, and for overview of Catalog to Fulfillment set up.
Copyright © 2011-2025 MUSC Foundation for Research Development