Meeting:

SPARC OS Technical Committee

Date:

08/17/22

Time:

3:00 pm - 3:17 pm

MUSC

Andrew, Greg, Brigette

Iowa

LA CaTS

Ying

Children’s National

Case Western

OHSU

Imogen

Stony Brook Medicine

Xin

Agenda:

Standup Round for institutional updates

...

Louisiana Clinical & Translational Science Center: 

08/03/22

08/17/22

...

MUSC:

08/17/22

Team

Current Items

Sherly

Matthew

Greg

James

Andrew

(SPARCRequest Step 4 and SPARCDashboard) Able to multi-select documents and download into Zip (https://www.pivotaltracker.com/story/show/166687325)

Ito

Jason(SPARCDashboard) Notification Email Linking Directly to Notification Message (https://www.pivotaltracker.com/story/show/165182951)

Ito

(SPARCDashboard) Tooltip Blocks Contact Names After Clicking on Message Button (https://www.pivotaltracker.com/story/show/179775902)

(SPARCFulfillment) Incorrect Protocol ID on Study Schedule Report (https://www.pivotaltracker.com/story/show/182732270)

Greg

Setting up Testing for (SPARCFulfillment) Add Flag for Participant Tracker Deletion Action to Improve Efficiency (https://www.pivotaltracker.com/story/show/180541541)

Working on (SPARCFulfillment) Subsidy Report Total Fulfilled and Total Invoiced Columns Calculation Improvements (https://www.pivotaltracker.com/story/show/178220264)

James

Debugging (SPARCRequest) Replace PaperClip with ActiveStorage (https://www.pivotaltracker.com/story/show/170086933)

Andrew

Pull requests, final RMID stories for product release

Jason

(SPARCRequest) Update Language in Search Bar to Provide Clear Instructions (https://www.pivotaltracker.com/story/show/175272932)

(SPARC-data structure) Combine Funding Source and Potential Funding Source (https://www.pivotaltracker.com/story/show/178306556)

...

Oregon Health & Science University:

...

  • Continued report refinements/clean up, data migration and confusion with user new account setups.

  • RMID issue resolved where configuration done to not force some of the required data fields

  • Inquired about the status of PT story SPARCRequest Step 2 and SPARCDashboard: Add Associated Organizations on Protocol Information Form. It is scheduled for the next SPARC release 3.10.0, however hasn’t been picked up yet for development work. MUSC is in the process of reviewing and prioritizing SPARC stories in planning its next release and will be sure to include this one in a status update.

08/17/22

  • Need clarification on required design for SPARCRequest Step 2 and SPARCDashboard: Add Associated Organizations on Protocol Information Form. The story describes a feature Case has built that’s similar to this one, potentially to make Case’s Project/Study Scope field optional and contribute that to the main repository. The next steps for this design will be determined. This is important for OHSU, but not urgent so may be ok to fit within a SPARC release timeline without OHSU taking on the development.

...

Iowa

08/03/22

  • Chris unable to attend

08/17/22

  • not on this week

...

Case Western

08/03/22

  • Jeremy unable to attend this week

08/17/22

  • Jeremy unable to attend this week

...

Children’s National

08/03/22

  • not on this week

08/17/22

  • not on this week

...

Stony Brook:

08/03/22

  • Implemented the delayed email fix discussed with MUSC and jobs have been running successfully so far.

  • Working to have clean data in dev site with goal to copy database over and use in production to avoid rebuilds. Discussed it may be best to export tables you want vs the whole database. It will be a manual process but may get the best dataset and be an easier clean up. Can reach out to MUSC to take a look when they are at this clean-up point.

  • Asked how to contribute Stonybrook’s feedback into PT stories. Andrew described the process of adding their name to the task (with priority ranking in parentheses) and then checking the box after saving. Can also include comments within the story. Send new story ideas to MUSC, where it can be reviewed, discussed in Operations governance and story entered for prioritization. Brigette also shared there are SOPs being drafted describing some of these processes that will be shared when finalized.

08/17/22

  • Working on testing data copied from dev server to the test server before moving to production. Sent database for MUSC to look at as advisement. Andrew will take a look at it.

  • Confirmed if service providers can delete services. They cannot do this, but services can be hidden from appearing in SPARC.

...

Update:

...

  • MUSC began looking in using MSTeams for group communication, per previous meeting inquiries.

Action Items: